Extension of Time (EOT) & Delay Impact Calculator
Model excusable vs non-excusable delays, revised completion milestones, compensable prolongation days, and concurrent delay overlaps.
Project Completion & Delay Log
EOT Assessment Summary
Day 125Project Completion Milestone Timeline & Delay Extension Curve
Detailed Delay Event Schedule
| Event Name | Category | Days | Excusable | Compensable | EOT Granted |
|---|
Frequently Asked Questions (FAQ)
What is an Extension of Time (EOT) in construction contracts?
An EOT is a contractual adjustment moving the formal project completion date outward, excusing the contractor from delay damages for owner-caused or force majeure delays.
What is the difference between Compensable, Excusable, and Non-Excusable delays?
Excusable & Compensable delays (owner fault/variations) grant extra time AND cost compensation. Excusable & Non-Compensable delays (neutral events/weather) grant extra time ONLY. Non-Excusable delays (contractor fault) grant neither.
Why must a delay impact the CPM Critical Path to qualify for an EOT?
Delays to non-critical tasks absorb available float without delaying overall project completion. An EOT is granted only if the event delays critical path activities.
What is a Condition Precedent notice requirement in EOT clauses?
Contracts (such as FIDIC Clause 20.1) mandate submitting a formal delay notice within a strict window (e.g. 28 days); failure to notify within time bars the EOT claim.
What is Concurrent Delay in EOT delay analysis?
Concurrent delay occurs when two independent delay events—one employer risk and one contractor risk—happen during the same time frame and both affect the critical path.
What is the Society of Construction Law (SCL) Delay and Disruption Protocol?
The SCL Protocol provides internationally recognized best-practice guidelines for analyzing delay, float ownership, concurrency, and EOT entitlement.
What delay analysis methodologies are commonly accepted in EOT claims?
Common methodologies include Time Impact Analysis (TIA), As-Planned vs As-Built, Collapsed As-Built, and Impacted As-Planned CPM schedule modeling.
What is constructive acceleration in construction contracting?
Constructive acceleration occurs when an owner refuses a valid EOT request, forcing the contractor to expend additional resources and overtime to meet the original completion date.
How does weather entitlement work under AIA A201 and FIDIC contracts?
To qualify for an EOT, weather events must exceed statistical 10-year historical averages for that month and location, and directly stall critical exterior work.
What prolonged preliminary costs can a contractor claim with a compensable EOT?
A contractor can claim time-related site overhead (site office rental, supervision salaries, equipment rental, utilities) incurred during the approved extended duration.
- AIA Document A201-2017 General Conditions of the Contract for Construction (§ 8.3 Delays and Extensions of Time)
- FIDIC Conditions of Contract for Construction (Red Book 1999, Sub-Clause 8.4 - Extension of Time for Completion)
- FIDIC Conditions of Contract for Construction (Red Book 2017, Sub-Clause 8.5 - Extension of Time for Completion)
- Society of Construction Law (SCL) Delay and Disruption Protocol (2nd Edition, 2017)
Legal & Professional Disclaimer: Estimates for planning and commercial evaluation only. Extension of Time entitlement and concurrent delay doctrines vary by jurisdiction, local contract amendments, and specific factual circumstances. Consult qualified legal counsel and claims specialists before submitting or resolving EOT claims. Not legal advice; no liability.