Trench Sloping & Benching Calculator
Calculate OSHA 29 CFR 1926 Subpart P excavation trench slope ratios, side cut runs, top opening widths, and protective system triggers.
Excavation Geometry & Soil Type
Sloping Dimensions
REQUIRED (Depth > 5 ft)Trench Cross-Section Sloping Diagram
Frequently Asked Questions (FAQ)
What is the OSHA 29 CFR 1926.651 excavation depth threshold requiring protective systems?
OSHA requires a protective system (sloping, benching, shoring, or shielding) for all trenches 5 feet (1.52m) or deeper, unless excavated in stable rock.
What is Type A soil under OSHA classification?
Type A is cohesive soil with an unconfined compressive strength of 1.5 tons per square foot (tsf) or greater (e.g., clay, silty clay).
What is the allowable sloping angle for OSHA Type A soil?
Type A soil requires a maximum sloping angle of 3/4:1 (53° above horizontal) for excavations up to 20 feet deep.
What is the allowable sloping angle for OSHA Type B soil?
Type B soil (angular gravel, silt, sandy loam, strength 0.5 to 1.5 tsf) requires a maximum sloping angle of 1:1 (45° above horizontal).
What is the allowable sloping angle for OSHA Type C soil?
Type C soil (granular soil, sand, gravel, submerged soil, strength < 0.5 tsf) requires a maximum sloping angle of 1.5:1 (34° above horizontal).
What ladder egress distance is required in trenches?
OSHA 1926.651(c)(2) requires a stairway, ladder, or ramp in trenches 4 feet or deeper, located so workers travel no more than 25 feet laterally to reach egress.
How far back must excavated spoil piles be set from the trench edge?
OSHA requires keeping spoil piles and equipment at least 2 feet (0.61m) back from the edge of the excavation to prevent cave-ins.
What duties are required of an OSHA Competent Person at a trench site?
A Competent Person must classify soil type, inspect trenches daily before worker entry, monitor atmospheric hazards, and order immediate evacuation if instability is detected.
What is trench shoring vs trench shielding (trench box)?
Shoring uses hydraulic or timber props to apply active pressure against trench walls to prevent soil movement. Shielding (trench boxes) protects workers inside if a collapse occurs.
When must trench safety systems be designed by a Registered Professional Engineer (PE)?
OSHA standards mandate that excavations deeper than 20 feet (6.1m) require a protective system designed and stamped by a licensed Professional Engineer.