Preliminaries & General (P&G) Calculator
Calculate time-related site management costs, fixed setup fees, percentage of works ratio, and delay prolongation claims under CSI Division 01 and FIDIC rules.
P&G Cost Inputs
P&G Cost Dashboard
P&G = 20.5% of WorksTime-Related vs Fixed P&G Monthly Distribution
Frequently Asked Questions (FAQ)
What are Preliminaries & General (P&G) costs in construction contracts?
P&G costs are jobsite management and site operational overhead costs required to run a project that cannot be allocated directly to a specific permanent work item.
What is the typical percentage range of P&G relative to total contract value?
P&G costs typically range from 8% to 15% of total contract value depending on project duration, complexity, site logistics, and regional market norms.
What items fall under Fixed Preliminaries vs Time-Related Preliminaries?
Fixed preliminaries are one-off setup costs (mobilization, hoardings, temporary utility connection). Time-related preliminaries scale with duration (site office rental, staff salaries, welfare facilities, security).
How are project management salaries allocated in P&G schedules?
Monthly salaries for project managers, site engineers, QS, safety officers, and foremen are extended over the baseline construction duration as time-related preliminary items.
What temporary utilities are included in site preliminaries?
Temporary power transformers, site lighting, water distribution, internet, and temporary site drainage setup and monthly utility bills.
How does an extension of time (EOT) impact time-related preliminary costs?
An approved compensable EOT entitles the contractor to claim prolonged time-related preliminaries for the extended duration.
What is the difference between Preliminaries and Main Office Overhead (Head Office Overhead)?
Preliminaries cover site-specific indirect operational costs, whereas head office overhead covers corporate administration, executive salaries, and offsite office rent.
How are contractor insurance policies budgeted in preliminaries?
Contractor's All Risks (CAR) insurance, Third-Party Liability (TPL), and Workmen's Compensation premiums are included as fixed preliminary cost line items.
What site security and safety provisions are estimated in P&G?
Perimeter fencing, security guard shifts, CCTV surveillance, PPE inventory, site signage, and first aid facility maintenance.
How does FIDIC Clause 13 handle variations to general preliminaries?
Under FIDIC conditions, if variation orders substantially increase project scope or duration, time-related preliminaries are adjusted pro-rata or by actual proven cost records.